WRA Clubhouse Project

In March 2018 White Rose Archers began digging the foundation of this clubhouse.  It was completed in 2019, our 75th anniversary year.

White Rose Archer’s Clubhouse – conceived and constructed by club members
Paul Howlett
8th March 2017 – A bare field
Ian Wright

6th June 2018 – Digging the foundations
Richard Hudson
8th June 2018 – Concrete delivered by pump
Ian Wright

Across the beautiful 300 year-old packhorse bridge club members carried:-

  • 52 tonnes concrete blocks
  • 23 tonnes sand, gravel and cement
  • 3 tonnes timber
  • 2 tonnes roofing sheet
  • 2 wash basins
  • 1 kitchen sink
  • 2 toilets and cisterns
  • 1 water tank
22nd July 2018 – Concrete breeze blocks for the walls waiting to be manhandled to the site
Paul Howlett
22nd July 2018 – Construction underway. Up to floor level!
Paul Howlett
30th October 2018
Ian Wright
2nd November 2018 – Starting to take shape
Richard Hudson
7th November 2018 – Wall to one elevation complete
Richard Hudson
6th November 2018 – Delivering and installing timber roof trusses
Paul Howlett
6th November 2018 – Roof taking shape
Paul Howlett
19th November 2018 – Timber roof trusses all in place
Richard Hudson
19th November 2018 – Roof sheeting being fitted
Richard Hudson
22nd November 2018 – Roof sheeting nearing completion
Richard Hudson
26th November 2018 – Building shell completed
Richard Hudson
11th December 2018 – Looking good in the sun
Richard Hudson
4th March 2019 – Interior. Walls, floor and ceiling painted, and one toilet being built
Richard Hudson
1st September 2019 – Finishing touches to the outside painting
Richard Hudson
30th September 2019 – Dai Hallgarth adding the finishing touches to the club logo
Richard Hudson
5th October 2019 – WRA Autumn Longbow Shoot. First view visitors had of our new clubhouse
Ian Wright

Members did the plumbing, electrical work, flag laying, step building, landscaping, demolition of old toilet/storage building, planting of 500 tree saplings, fitting of wind turbine and solar panel, flooring, ceiling and roof insulation, painting inside and out.  Approximately 3,500 hours labour at a total cost of £35,000 being well under half of  the estimated cost.